Thankyou, all, for your input!
I do understand about determining which loads are required for starting up the plant, and going from there.
What I am looking for is anyone that is knowledgeable about or has direct experience with these exact circumstances - i.e. static frequency converter (sfc) starting of a gas turbine generator (rated ~ 200MVA) under black start conditions.
The sfc is part of the gas turbine generator package. Although, I do not have the exact specifications for this unit, on other units I've seen, the sfc is comprised of a transformer, with other components - converters, inverter - connected to its load/low voltage side. Rating is about 5000kva, 4160V.
My question is based on having no experience with providing black start capability with this type of configuration - medium voltage input requirement for sfc, etc., do I need one or two diesel generators, 100% vs. 50% each, what should their output voltage be, etc..