richanton
Electrical
- Jul 15, 2002
- 128
Just interested in some opinions on this topic. My building is 40 years old. We are replacing the original motor control centers. The original cables used are older fabric insulated cables run underground in the original bldg slab. I want to replace the feeder cables for reliability, since I am putting a new MCC in. Question is, what are the odds that I can pull out the old cable and put new cable in. Right now, I am thinking it's a bad idea and I should put new overhead conduit and cable in. The run length is probably about 150-200 feet.