WhatsGoingOn
Industrial
- May 3, 2006
- 8
I hope this is appropriate, I have some questions regarding a current repair job to a central two story garage in my townhouse complex. I am stepping outside my knowledge base, please excuse any abuse of terminology. I am based in Ontario.
We were told we needed to replace the waterproof membrane on the top of the parking structure (no roof) and repair some delaminated concrete. We hired a consulting Engineer to write up the specs and oversee the project. Original quote was 200K. Three weeks into the job they have now said the entire slab requires replacement, and the project is now closer to 500K. The slab is ~10600ft².
1) It was discovered that an original 8" slab was topped with a 4" slab, likely about 20 years ago. It was recommended the slab should be removed and we did so. It was at least a couple of days between the first concrete removal and us being alerted about the issue.
2) Areas were mark for concrete removal. Bridging was installed and they have been going at it with jackhammers. No forming plywood was put underneath intially which some unit owner found suspicious, but the project Engineer stated this goes up later. Does this sound right?
3) I would think an initial core sample would have pointed out the double layer of concrete. The engineer stated they don't always deem it necessary, is this the case? Core samples were taken after the top layer was removed, tested at 36 MPA, but they feel the concrete had deteriorated beyond reuse. When trying to remove the bad spots, they can't get to good concrete to bond with.
We were told we needed to replace the waterproof membrane on the top of the parking structure (no roof) and repair some delaminated concrete. We hired a consulting Engineer to write up the specs and oversee the project. Original quote was 200K. Three weeks into the job they have now said the entire slab requires replacement, and the project is now closer to 500K. The slab is ~10600ft².
1) It was discovered that an original 8" slab was topped with a 4" slab, likely about 20 years ago. It was recommended the slab should be removed and we did so. It was at least a couple of days between the first concrete removal and us being alerted about the issue.
2) Areas were mark for concrete removal. Bridging was installed and they have been going at it with jackhammers. No forming plywood was put underneath intially which some unit owner found suspicious, but the project Engineer stated this goes up later. Does this sound right?
3) I would think an initial core sample would have pointed out the double layer of concrete. The engineer stated they don't always deem it necessary, is this the case? Core samples were taken after the top layer was removed, tested at 36 MPA, but they feel the concrete had deteriorated beyond reuse. When trying to remove the bad spots, they can't get to good concrete to bond with.