MikeE55
Structural
- Aug 18, 2003
- 143
I am designing an addition which requires removing about 100 feet of load bearing wall (also serves as shear wall for a single story bldg). I'm replacing it with posts and beams and making frames rigid to handle the lateral loads. This wall supports bar joists spanning about 25 feet. My past procedure is to state on the plans "provide shoring as required". Should the plans include shoring design? I think this is part of the contractor's means and methods, and I don't want to design it. But should I ask for the shoring design to be submitted for approval, and sealed by a PE, etc. What's your standard practice?