It means restoration of the site to preconstruction conditions.
"The pipeline running track and trench is reinstated to grade level using the topsoil that has been stored to one side of the running track during the first of the ROW preparation works. The intention during the reinstatement works is return the whole of the construction occupied areas to their former condition.
The key areas that require full reinstatement are the ROW, the construction camps and storage areas, the block valve sites and the new temporary access roads. The project reinstatement specification is generally based on the following principles:
•Disturbed areas will be reinstated to pre-construction conditions to the greatest practicable standards. This to include for bio-restoration, species translocation, reseeding and replanting and maintenance with the correct measures implemented to include for pest control, weeding and avoidance of introducing or the spreading of foreign/invasive species and notifiable diseases.
•There may be a continuing requirement for access along the ROW by patrols and for maintenance.
•Levelled working areas on side slopes and ridges may be retained to allow future access for inspection and maintenance.
•Disturbed areas will be stabilised to protect the integrity of the pipeline and minimise potential impacts associated with erosion, transportation and sedimentation of material from disturbed areas.
•Disturbed areas will be re-vegetated to achieve conditions similar to those that exist immediately adjacent to the ROW.
•Regular monitoring and maintenance of all reinstated areas will be undertaken until environmental requirements and goals are achieved. The commitment to monitor the success or otherwise of the reinstatement plan can vary and can be anything up to a period of ten years, The developer then remains the responsible body for any further reinstatement or erosion control work for the life of the development
As well as reinstating the pipeline ROW any temporary areas previously occupied by the construction activities must also be reinstated to their preconstruction condition As mentioned earlier (see Section 15.9) a record of condition report will have been undertaken before works begin and this will prove to be a useful tool in assessing what (if any) damage to land, property, access roads, etc., is attributable to the pipeline build and what is needed to reinstate the matter to its former condition should any repair be deemed necessary."