Jul 26, 2006 #1 Londoner Computer Joined Jul 17, 2006 Messages 2 Location GB when i set a task to recur for a meeting the duration is not right. to test i set a simple 8 hr 2 day task and recurring it over 2 days with resource on 4 hrs shows duration 1.5 not 1
when i set a task to recur for a meeting the duration is not right. to test i set a simple 8 hr 2 day task and recurring it over 2 days with resource on 4 hrs shows duration 1.5 not 1