3.11 Access Road Surfacing
A. Subgrade shall be moisture conditioned and prepared as necessary to meet the final surface performance specified under paragraph D of this subsection.
B. Placement shall be by methods that will minimize segregation. Any damage to underlying or surrounding material or structures during placement of the millings shall be repaired before proceeding with the work.
C. Asphalt millings shall be placed to full layer thickness in one operation in such a manner as to minimize segregation and avoid damage to underlying materials.
D. Asphalt millings shall be road mixed with an emulsion/rejuvenator application rate of 0.25 Gal/SY – Inch. The mixed asphalt millings shall have a total moisture content of 6% by weight and be compacted to 95% of Standard Proctor Density.
E. Compaction shall be achieved by a smooth drum vibratory compactor, or other equipment approved by the ENGINEER. Roller shall make a minimum of three passes in each direction over the asphalt millings. Roller direction shall be in both the longitudinal and lateral direction .(perpendicular to the centerline of the road). Prior to acceptance, the surface of the placed asphalt millings shall be proof-rolled and shall be smooth, firm and unyielding. At the completion of this activity no wheel ruts or other irregularities shall remain on the surface. Place asphalt millings to the lines, grades, cross sections, and dimensions shown on the drawings.