The concrete pour for this balcony has been pushed off a few days due to weather conditions, which gives me more time to obsess over my details.
Thank you everyone for your help thus far.
Here are my specific questions:
After reading alot of posts on how cracking occurs in suspended slabs, I fear that we will have cracking at the 3 1/2" end. The owner is open to the idea of forming the slab edge as needed to provide a 4 1/2" slab at the left end. Of course I will have egg on my face if I encourage them to take this action, but would rather have the egg then to have them have a product they aren't happy with.
Per my vulcraft catalog, this deck is good for a superimposed live load of 220 psf (much much more than what I need), which is why I was comfortable going down to the 3 1/2" thickness at the low end.
[ul]
[li]Are the clear distances to the rebar OK?[/li]
[li][/li]
[li]Can I just tie the #4 bar to the WWF instead of introducing tie bars?[/li]
[li][/li]
[li]Do I really need to hook the end of the #4 bar? I am currently showing it unhooked.[/li]
Will these #4 bars do more harm than good? Will it be too heavily reinforced?
[/ul]