Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Ramp Mesh 1

Status
Not open for further replies.

MN91

Civil/Environmental
Jul 1, 2015
4
Dear fellow engineers,

In the attachment below is a ramp supported along the x-direction, and having the ramp-basement wall connection fixed by epoxy (y-direction).

My question is, is there any structural deficiency if the ramp steel reinforcements were placed in such a way having the Y-reinforcements placed first, then having the X-reinforcements laying on it?

Best Regards
 
 http://files.engineering.com/getfile.aspx?folder=d1700751-922b-4e2a-bbef-84e8f40c1fa2&file=Ramp_Section.jpg
Replies continue below

Recommended for you

I can't decipher your plan. Maybe someone else can. What is the span? The bottom bars should be placed first in the direction of the span.

What are the numbers? Dimensions? Not in the dreaded centimetres, I hope.

Epoxy is not a way to fix a slab to a wall.
 
From what I understand, you want the ramp to one way span between two walls.

And you are asking whether it's bad to lay your secondary reo down first and then the main flexural reo on top.

It's structurally inefficient as you are losing effective depth (by the diameter of your secondary bar) to the bottom main flexural steel.

 
Like Trenno said, the only potential issue is inefficiency if your largest moments wind up being resisted by your shallower effective depth. A 350 slab is fairly thick. The efficiency penalty ought no be that bad.

I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.
 
Turn in your engineering membership card... I see centimeters.

 
Status
Not open for further replies.

Part and Inventory Search

Sponsor