GarthJ
Structural
- Dec 7, 2006
- 10
I am designing a soldier pile cofferdam (25'x30' plan dims)directly under some railroad tracks. The tracks will span across the cofferdam on a temporary bridge. There is no question that the full surchage (2000 psf for Cooper E80) must be applied to the sides of the cofferdam that are perpendicular to the tracks. I'm wondering about the sides of the cofferdam that are parrallel to the tracks. Does this surcharge have to be applied to these sides?