jgibbs22
Mechanical
- Jun 13, 2008
- 80
Hi:
Got a two part question for everyone. In a non-lethal, 10,000 psi pressure vessel, would a 1/2" grayloc hub being used as a nozzle on a hemispherical hub be required to have radiography performed on the weld? I did not think so due to the size and not using table UW-12 values in the design but wanted to confirm.
Secondly, if RT was performe even if not required and incomplete penetration was discovered, would it still be considered Code rejectaboel and need to be repaired even if the RT was not required in the first place?
Thanks!
Got a two part question for everyone. In a non-lethal, 10,000 psi pressure vessel, would a 1/2" grayloc hub being used as a nozzle on a hemispherical hub be required to have radiography performed on the weld? I did not think so due to the size and not using table UW-12 values in the design but wanted to confirm.
Secondly, if RT was performe even if not required and incomplete penetration was discovered, would it still be considered Code rejectaboel and need to be repaired even if the RT was not required in the first place?
Thanks!