Dear all,
I am working in a power plant construction project. As per radiography requirement stated in technical specification 10% radiography to be taken for Water wall panel joints. My problem is how to select joints for radiography..? shall I offer 10 % of total joints welded so far or shall I go 10 % of welder wise joint made per day per shift ..?
Kindly suggest.
I am working in a power plant construction project. As per radiography requirement stated in technical specification 10% radiography to be taken for Water wall panel joints. My problem is how to select joints for radiography..? shall I offer 10 % of total joints welded so far or shall I go 10 % of welder wise joint made per day per shift ..?