Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations JAE on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Question on Flange To Shell Weld Stress

Status
Not open for further replies.

sixgpipewelder

Industrial
Joined
May 26, 2013
Messages
2
Location
US
Hi,
I am a newbie 6G pressure vessel welder and have a question. I backwelded a flange onto a carbon steel separator shell (GMAW Root, FCAW Fill & Cap). My superviser told me that because I didn't weld the OD right away that I run the risk of cracking the back weld when I go to weld the outside. Is this true? Wouldn't preheating both sides avoid this event? I would appreciate any tips on this as I have to finish this weld Tuesday and there are a few internals I would have to remove to fix this if it fails. I have looked everywhere for info and this is the only site I have faith in. Thanks. Stanley
 
Not true for welding carbon steel pipe materials (see B31.1 and interruption of welding). For low alloy steels, like P-No 3, 4 and 5A, yes, there is a risk of cracking, which is why a minimum deposit thickness is required and visual examination (before welding begins again) should welding be interrupted (loss of preheat).
 
Can't say I've ever heard of it. We just qualified some procedures with a delay (> 8 hours) to cover those welds where a few runs were completed prior to knock off time. These are pipe welds and not your design but same principle.
 
Thanks for the responses. I never had any issues with cracking as long as I pre-heated when restarting any welding. I appreciate the info without getting "flamed" for my lack of knowledge. Thanks again. Stanley
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top