Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations TugboatEng on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Question for Structural Guys

Status
Not open for further replies.

abusementpark

Structural
Joined
Dec 23, 2007
Messages
1,087
Location
US
From what I have been told, the most common way firms are paid for structural services on mid to large projects is to agree to a certain percentage of the construction bid. I guess this is preferred to lump sum in case the scope of work changes significantly.

I was just wondering what that percentage usually is? And is it the total construction fee or just the structural portion??

Thanks.
 
I have been around when some conversations have taken place and I believe we typically get around 1% of total construction costs. That really doesn't seem like much. Even on a $25M project it's only $250K. Well, maybe that is a decent amount. If it utilizes 2 engineers for a 3-5 month period for design, I guess the principals are making out alright!!
 
Even with that fee, I would still charge an extra hourly based fee for changes in design requiring repeat or additional structural engineering. Remember the name of the boat posted in a picture in the forum a few months back that was the contractor's tender? There's a lot of $$$ to the contractor for changes.

Mike McCann
MMC Engineering
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top