Olid
Mechanical
- May 22, 2003
- 95
Hello all,
We finally switched from Smarteam to PDMWorks and I have a lot to learn. One of our users is asking me if there is a way to have assemblies check out of the vault with "latest released" components like we did in Smarteam. I know that we can always get the latest, however the latest might not be released.
We have set up our vault to have only two life cycle stages, "in process" and "released" and I don't see how we can get the "latest" released parts. We can only get "as built" or the "latest versions".
How do others handle this?
BTW
We are on SW2006 SP3.4 & PDMW 3.0 build 0051
Regards,
Dan Olid
We finally switched from Smarteam to PDMWorks and I have a lot to learn. One of our users is asking me if there is a way to have assemblies check out of the vault with "latest released" components like we did in Smarteam. I know that we can always get the latest, however the latest might not be released.
We have set up our vault to have only two life cycle stages, "in process" and "released" and I don't see how we can get the "latest" released parts. We can only get "as built" or the "latest versions".
How do others handle this?
BTW
We are on SW2006 SP3.4 & PDMW 3.0 build 0051
Regards,
Dan Olid