We need to weld a temporary cap (P1) to a (P4) pipe for a shop hydro-test of a spool piece. The only qualified weld procedure we have requires PWHT. Is there any exemption/code case/interpretation that allows us to perform the weld, perform the hydro, and cut out the weld. All without PWHT?
Thanks in advance