pwht of 9 chrome

Status
Not open for further replies.

tomp75

Petroleum
Joined
Dec 19, 2010
Messages
1
Location
US
When completing a 9 Chrome butt joint, are there any code requirements or standard practices that state the welded joint should be pwht within a certain number of days? Also, what should be done with a welded pipe butt joint that is about one half finished and then not completly finished for seven to fourteen days?
 
tomp75,
What code are you working to ?
Different codes have different criterias for PWHT,
Regards,
Kiwi
 