Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

PWHT according to AWS D1.1

Status
Not open for further replies.

fakhmed

Mechanical
Dec 24, 2002
15
Dear All,

When looking in the AWS D1.1 (contractual standard) I don't find any direct requirement to perform or not a PWHT of full penetration butt weld of carbon steel plates thickness 50mm up to 105mm.

Can some body help me in order to decide if it is required or not to perform a PWHT for such a welds?

Thanks in advance.
[ponder]
 
Replies continue below

Recommended for you

It is up to the designer or contractor to deside if PWHT is required. With the thickness you mention I would say it is adviced to do a PWHT.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor