I'm working on an isolated water distribution system that is serviced by a pump station and water tank. The water tank satisfies the fire flow demand, however it is a steel tank that will need to be taken off-line every 15 years to be refinished for 1-2 months. Generally, the pump station's sole purpose is to fill the water tank.
Does the pump station need to be sized to meet the fire flow demand during the down time even though its so infrequent? This results in a significant up sizing of the pump station. Or can are there alternate measures that can be put in place during the down time?
Does the pump station need to be sized to meet the fire flow demand during the down time even though its so infrequent? This results in a significant up sizing of the pump station. Or can are there alternate measures that can be put in place during the down time?