mweng
Civil/Environmental
- Nov 15, 2002
- 29
How do you show project finish dates that are based on the actual start and % completion? For example, I have schedule where I entered actual start of 11/12/03, duration is 10 working days and task is 80% complete. Project is showing a finish date of 11/25/03. How can this be true if today is 3/4/04 and the task is not yet complete?