Nov 6, 2006 #1 Dazzer96 Computer Joined Nov 6, 2006 Messages 4 Location GB Is there any way in which i can make a certain time period unusable. But i wish tasks to still be used before that time and then carry on with that task after. E.g. if there is a strike.
Is there any way in which i can make a certain time period unusable. But i wish tasks to still be used before that time and then carry on with that task after. E.g. if there is a strike.
Nov 6, 2006 #2 IRstuff Aerospace Joined Jun 3, 2002 Messages 44,895 Location US I don't know if there's a cleaner way, but why can't you set those days to be non-working in the project calendar? TTFN Upvote 0 Downvote
I don't know if there's a cleaner way, but why can't you set those days to be non-working in the project calendar? TTFN
Nov 6, 2006 Thread starter #3 Dazzer96 Computer Joined Nov 6, 2006 Messages 4 Location GB i know this sounds stupid but i tried looking for that option but couldnt find it. Upvote 0 Downvote
Nov 6, 2006 #4 IRstuff Aerospace Joined Jun 3, 2002 Messages 44,895 Location US Go to Tools|Change Working Time Select a date on the calendar and select your choice from the "Set selected date(s) to:" on the right hand side TTFN Upvote 0 Downvote
Go to Tools|Change Working Time Select a date on the calendar and select your choice from the "Set selected date(s) to:" on the right hand side TTFN
Nov 6, 2006 Thread starter #5 Dazzer96 Computer Joined Nov 6, 2006 Messages 4 Location GB mmmm i am using 2003 and dont see that optuion, there isnt a right side it you understand me? Upvote 0 Downvote
Nov 6, 2006 Thread starter #6 Dazzer96 Computer Joined Nov 6, 2006 Messages 4 Location GB HAHA i found it! it was under tools and change the work day. Thanks alot pal you just saved about 10 students at uni from failing on our deadline tomorrow Upvote 0 Downvote
HAHA i found it! it was under tools and change the work day. Thanks alot pal you just saved about 10 students at uni from failing on our deadline tomorrow