Project help

Status
Not open for further replies.

Dazzer96

Computer
Nov 6, 2006
4
Is there any way in which i can make a certain time period unusable. But i wish tasks to still be used before that time and then carry on with that task after. E.g. if there is a strike.
 
Replies continue below

Recommended for you

I don't know if there's a cleaner way, but why can't you set those days to be non-working in the project calendar?

TTFN



 
i know this sounds stupid but i tried looking for that option but couldnt find it.
 
Go to Tools|Change Working Time

Select a date on the calendar and select your choice from the "Set selected date(s) to:" on the right hand side

TTFN



 
mmmm i am using 2003 and dont see that optuion, there isnt a right side it you understand me?
 
HAHA i found it! it was under tools and change the work day.

Thanks alot pal you just saved about 10 students at uni from failing on our deadline tomorrow :)
 