Below is a typical close out report table of contents that may help.
Section 1.0 EXECUTIVE SUMMARY
1.1 Scope of Work
1.2 Contractor & Location
1.3 Project Organization and Execution Plan 1.4 Contract Structure
1.5 Project Priorities
1.6 Safety
1.7 Quality
1.8 Cost
1.9 Schedule
1.10 Teamwork - several paragraphs
1.11 Lessons Learned
1.12 Positive Highlights & Observations
Section 2.0 SAFETY
- Statistical performance (Planned vs. Actual)
- Site Safety Teams
- Safety initiatives (Summary)
- Incident Investigations - Summary
- Near miss investigations - Summary
- Safety meetings - Summary
Section 3.0 QUALITY See Construction Site Quality Closeout Report Template
Section 4.0 COST & PROJECT CONTROL
Section 5.0 SCHEDULE & MANHOURS
As-built schedules (Schedules)
(Manhour & quantity data)
Section 6.0 TEAMWORK
Section 7.0 PROJECT EXECUTION PLAN
Section 8.0 DISCIPLINE OR AREA REPORTING (Use only those sections which apply to the Construction Site)
Each Discipline should cover:
* Special safety considerations (examples: Structural - risk assessments, rigging reviews)
* Quality (examples: Structural - dimensional control; Mechanical - hydro test; E&I - loop checks? * Productivity metrics (examples: Structural - man-hours per ton; Mechanical - man-hours/spool; E&I - legions per 100 m cable tray)
* Lessons learned hi-lights (detailed lessons learned in an appendix)
* Special topics (examples: Structural - erection sequence, scheduling, load-out, materials, fiberglass grating; Mechanical - iso scheduling, hydro-test, TCP's, vendor data incorporation; E& I - TCP's
Section 8.1 STRUCTURAL or AREA 1
Section 8.2 MECHANICAL PIPING or AREA 2
Section 8.3 ELECTRICAL & INSTRUMENTATION OR AREA 3
Section 8.4 PRE-COMMISSIONING or AREA 4
- Schedule
- Punch-list handover
- TCP's
- Mechanical completion
- Post-load-out activities
- Carry-over punch list
Section 8.5 Hook up
Section 8.6 Commissioning
Section 8.7 Installation
Section 8.8 Start up
Section 9.0 PAINTING
Section 10.0 SCAFFOLDING
Section 11.0 INDIRECTS & CONSTRUCTION EQUIPMENT
Section 12.0 MATERIALS (Buying, Receiving, Warehousing, etc.) Input required from Teddy Bear, MM, and Snake
Section 13.0 ADMINISTRATION
- Organization charts/Staffing History (Planned vs. Actual)
- Filing System
- Tabular list of procedures developed
- Lessons Learned
Section 14.0 ACCOUNTING PRACTICES
- Time keeping
- Audits
- Invoice payments
- Lessons learned
Section 15.0 CONTRACTS & SUBCONTRACTS
Section 16.0 DOCUMENT CONTROL & ENGINEERING
Section 17.0 PHOTOGRAPHS
Section 18.0 Videos
Appendices As required
Greg Lamberson, BS, MBA
Consultant - Upstream Energy