Project & Last Planner

Status
Not open for further replies.

JeffMorris

Civil/Environmental
Joined
May 9, 2002
Messages
4
Location
GB
I am currently trying to establish a method of being able to show next weeks scheduled work alongside workable backlog (ie items not identified to be done next week, but those that can be done). And not display items that are not scheduled for next week or identified as workable backlog.

We have tried various filters and sorts but with little success, we are using Project 2000.

Thanks,

Jeff
 
I was able to get this to work by copying the "date range" filter, then add the follwing line:
AND %Complete is less than 100%
(Call it something like 'date range and incomplete')
Good luck!
 