Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Project & Last Planner

Status
Not open for further replies.

JeffMorris

Civil/Environmental
May 9, 2002
4
I am currently trying to establish a method of being able to show next weeks scheduled work alongside workable backlog (ie items not identified to be done next week, but those that can be done). And not display items that are not scheduled for next week or identified as workable backlog.

We have tried various filters and sorts but with little success, we are using Project 2000.

Thanks,

Jeff
 
Replies continue below

Recommended for you

I was able to get this to work by copying the "date range" filter, then add the follwing line:
AND %Complete is less than 100%
(Call it something like 'date range and incomplete')
Good luck!
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor