RJP78
Geotechnical
- Jan 11, 2005
- 6
To give some background, an assembly table, which is prone to the slightest movement, was placed on an existing 6 inch slab-on-grade within an industrial building. However, the table would become out of level by a few thousandths and fluctuate over time. As a result, the slab was reportedly torn out, some excavation below subgrade occurred, and an 18-inch independent slab (with #5 bar @ 12" OC) was poured. I've been informed that the subgrade consists of relatively fine sand fill, and was compacted prior to slab construction. Nevertheless, the problem persists. As a demonstration, a small forklift was positioned on a corner of the slab and it temporarily settled 0.007± inches.
Some additional information:
- Slab/mat measures 20'x16'x1.5'
- Assembly table weighs approx. 3 tons
- Facility has experienced temporary flooding of the shop floor in recent months.
- Overhead cranes and forklift traffic are present in the area of the table.
I've been asked to evaluate why the slab continues to move even after replacement. Since the slab will remain in place (for now at least), my observations and testing capabilities are limited. To determine the soil and water conditions present beneath the slab, cores alongside the slab are planned, with hand-augered sampling below.
Has anyone experienced similar scenarios? Can this small of movement be stopped, and by what means? Helical piers? Polymer injection?
Thanks for your time. I've been a long time lurker and am thankful for everything I've learned over the years on this site.
Some additional information:
- Slab/mat measures 20'x16'x1.5'
- Assembly table weighs approx. 3 tons
- Facility has experienced temporary flooding of the shop floor in recent months.
- Overhead cranes and forklift traffic are present in the area of the table.
I've been asked to evaluate why the slab continues to move even after replacement. Since the slab will remain in place (for now at least), my observations and testing capabilities are limited. To determine the soil and water conditions present beneath the slab, cores alongside the slab are planned, with hand-augered sampling below.
Has anyone experienced similar scenarios? Can this small of movement be stopped, and by what means? Helical piers? Polymer injection?
Thanks for your time. I've been a long time lurker and am thankful for everything I've learned over the years on this site.