Good morning, I'm quite new to MSP and require a degree of help. i'm sure this will be an easily resolved problem for someone with a bit of experience, but I'm stuck!!
I've entered a task's duration as 24 months (I've also tried 730 days with the same effect) and the automatically produced end date is exactly 2 months short of 2 years from the start date. i think i've set up my working hours / days etc correctly so i'm not sure what the issue is.
any help would be appreciated.
Regards
Tom
I've entered a task's duration as 24 months (I've also tried 730 days with the same effect) and the automatically produced end date is exactly 2 months short of 2 years from the start date. i think i've set up my working hours / days etc correctly so i'm not sure what the issue is.
any help would be appreciated.
Regards
Tom