LynnH
Mechanical
- Feb 22, 2002
- 5
Sometimes, I have a task (sucessor) with one predecessor. The predecessor complete date and the sucessor start date have a huge gap between them, and there's no obvious reason; the sucessor is not part of a summary task with a later date and the sucessor isn't tied to a later task either. The only way I can fix it is to recreate the sucessor, and I type in the same predecessor and successor; then it works. Does anybody know how to fix this? Thanks Much!