jonathanwilkins
Civil/Environmental
- Mar 13, 2007
- 47
In my area (southeast), metal building foundations are typically monolithic pours with large footers at the columns and hairpins to handle the thrust. Control joints are typically placed at 10-12' o.c. to prevent cracking. This is typically not overly detailed and from a purely technical standpoint somewhat flawed. This is, however, how it's been done and how I was taught (buildings are typically small) so it's what we do.
In a recent building, the concrete was cut with joints 20' and 25' o.c. I have not looked at it but the contractor has said that some cracking has started.
What's the best way to address these cracks or should we? Thanks.
In a recent building, the concrete was cut with joints 20' and 25' o.c. I have not looked at it but the contractor has said that some cracking has started.
What's the best way to address these cracks or should we? Thanks.