We are evaluating the design, schedule,installation costs and other requirements for a new packaged auxiliary (start-up) boiler for a fossil fired power plant. It will operate 400-500 hrs/year and be of conventional packaged "D" tube design
The boiler will be used only during the start-up phase of operation to provide DA pegging steam, gland steam for the main turbine and to get the boiler feed pump turbine rolling. Most of the time the new aux boiler will be in "hot standby" condition.
What design features should be included in the new aux boiler ?
We are going to include:
- Warming coil in the lower mud drum
- Stack damper to keep heat "in the box"
Any other suggestions based on experience ?
Regards
-MJC
We are evaluating the design, schedule,installation costs and other requirements for a new packaged auxiliary (start-up) boiler for a fossil fired power plant. It will operate 400-500 hrs/year and be of conventional packaged "D" tube design
The boiler will be used only during the start-up phase of operation to provide DA pegging steam, gland steam for the main turbine and to get the boiler feed pump turbine rolling. Most of the time the new aux boiler will be in "hot standby" condition.
What design features should be included in the new aux boiler ?
We are going to include:
- Warming coil in the lower mud drum
- Stack damper to keep heat "in the box"
Any other suggestions based on experience ?