Marmite
Electrical
- Jan 4, 2007
- 736
In a power plant where the station auxiliaries are fed from 2x 132/11kV transformers straight onto the station main 11kV switchboard, and the generator is separately connected to a 11/132kV delta star step up transformer feeding straight to a 132kV C/B on the 132kV bar at the main substation with no other 11kV connection and no unit transformer, would it be normal to provide a generator circuit breaker at 11kV? The consultants are suggesting that an 11kV generator circuit breaker is required, and one of the reasons cited is to earth the LV winding of the 132/11kV generator transformer for work on the transformer. It's an expensive way of providing an earthing facility, and personally I can't see why it would be required. Is the generator circuit breaker normally installed in this kind of scenario?
The generator will be connected to the generator transformer using 11kV phase segregated bus ducting.
I'd be grateful for any comments.
Regards
Marmite
The generator will be connected to the generator transformer using 11kV phase segregated bus ducting.
I'd be grateful for any comments.
Regards
Marmite