Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Post Weld Heat Treatement Requirement in ASME IX

Status
Not open for further replies.

BFZHA

Mechanical
Oct 29, 2009
33
Hi;
Actualy we are working on a WPS for an isolating joint wich have a material with P Number P1 and thickness up to 31.75 mm. Due to welding temperature (250°C)we did not specify a Post Weld Heat Treatement.
We want to know if PWHT requirement is indicated in ASME IX or another standard.
Regards.
 
Replies continue below

Recommended for you

The requirement for PWHT of the involved weld is not in ASME IX. It will be in some other Code; e.g., B31.1, B31.3, B3.4, B31.8, ASME I, ASME VIII, etc. If the design/construction Code were ASME VIII, Div.1, your weld would be exempt from PWHT.

 
BFZHA, it depends on your piping code, what kind of facility are you building and to what code?

As much as possible, do it right the first time...
 
Thanks for your reply,
The piping code is ASME B31.8 and ASME VIII Div.1.
 
It may also depend on the fluid service. Requirements for sour service may dictate that PWHT is required if the hardness maxima cannot be achieved without it.

Steve Jones
Materials & Corrosion Engineer

 
Assuming that PWHT is not required for service as per SJones, PWHT is not required per 825.2 od B31.8. If T exceeds 31.75mm (1 1/4"), PWHT is required.

 
Status
Not open for further replies.

Part and Inventory Search

Sponsor