AELLC
Structural
- Mar 4, 2011
- 1,339
In my area, we have moderately expansive clayey-sand soils and we use uniform thickness 7.5" thick PT slabs (not ribbed), with a 12" wide x 12" deep perimeter turndown on the exterior. Typically, we have PT tendons from 2-4" to 5-0" on center.
What I have is a very large custom home, with the plan being in a sort of "W" configuration. Obviously, it would be impossible to run tendons in an orthogonal grid system.
Would it be feasible to separate the plan with construction joints, meaning the slab would be poured in 3 or 4 different stages, with the tendons stressed at each succeeding stage, and each stage of the slab connected with #4 rebar dowels at 24" o/c? The slab would be thickened to 12" at those construction joints?
What I have is a very large custom home, with the plan being in a sort of "W" configuration. Obviously, it would be impossible to run tendons in an orthogonal grid system.
Would it be feasible to separate the plan with construction joints, meaning the slab would be poured in 3 or 4 different stages, with the tendons stressed at each succeeding stage, and each stage of the slab connected with #4 rebar dowels at 24" o/c? The slab would be thickened to 12" at those construction joints?