Yeah, that is what I found. I searched every spec concerning repair and PWHT under different P groups and could only find allowance for pipe and tubing 4" and less with wall thickness of .625 for P4 material. I figured I'd ask to see if I missed something. Thanks.
Not only re-PWHT, I think you might also need to check your PQR, see how many cycle of PWHT is done there, if there is any extra cycles done to cover further repair, to ensure properties of the weld, parent material and HAZ are still ok. If your application high temperature.