I have a situation where the contractor is building a train depot and have casted the soffit slab but missed a wall under the depot slab. The main problem is that the contractor has also not left any hanging starter bars for the construction of the wall.
I understand that there are post drill injection grout/epoxy systems, but my question is that most grouts are flowable so how do you grout it without all the grout leaking out?
Is there a injection system that can be used with a patch-up method instead to ensure the grout stays where it is?
Thanks!
I have a situation where the contractor is building a train depot and have casted the soffit slab but missed a wall under the depot slab. The main problem is that the contractor has also not left any hanging starter bars for the construction of the wall.
I understand that there are post drill injection grout/epoxy systems, but my question is that most grouts are flowable so how do you grout it without all the grout leaking out?
Is there a injection system that can be used with a patch-up method instead to ensure the grout stays where it is?
Thanks!