fastline12
Aerospace
- Jan 27, 2011
- 306
I have been scratching my head for some time here as I work on a design for a couple buildings I need. I will be building wood pole buildings and all poles, or rather multi-plied 2x materials, buried in the ground approx 4ft and concreted in place. After some research, I will find a solution to isolate the wood poles from soil contact to increase building life since that seems to be a common failure mode in them.
however, living in Tornado alley, I have to plan for complete structural failure in which breaking the beams at the ground is what would likely happen. The issue is that once they are broke, there is no way to replace them such as a steel I-beam building. The concrete piers are poured around the poles, then the floor is poured over that so everything is locked up solid. Even if I decide to raise the pier pour to concrete pad height, that means jack hammering out a LOT of poles.
I would love to come up with a solution that would allow me an easier repair should the need arise. Does anyone have an idea here? The only other thought I had was to run a huge auger through the 4ft of buried lumber to extract it, repour that as concrete, and use that as my support pier for I-beam construction BUT the issue is dimensionally, the building will be made for wood structure and I am sure trying to make that work with I-beam will not work out. Much easier to go back with wood.
The reason for selecting wood unfortunately has to do with my county appraiser and taxes. The steel building will cost me TWICE as much in taxes and continue to go up, while the pole will decline.
however, living in Tornado alley, I have to plan for complete structural failure in which breaking the beams at the ground is what would likely happen. The issue is that once they are broke, there is no way to replace them such as a steel I-beam building. The concrete piers are poured around the poles, then the floor is poured over that so everything is locked up solid. Even if I decide to raise the pier pour to concrete pad height, that means jack hammering out a LOT of poles.
I would love to come up with a solution that would allow me an easier repair should the need arise. Does anyone have an idea here? The only other thought I had was to run a huge auger through the 4ft of buried lumber to extract it, repour that as concrete, and use that as my support pier for I-beam construction BUT the issue is dimensionally, the building will be made for wood structure and I am sure trying to make that work with I-beam will not work out. Much easier to go back with wood.
The reason for selecting wood unfortunately has to do with my county appraiser and taxes. The steel building will cost me TWICE as much in taxes and continue to go up, while the pole will decline.