We are trying to start up some 1.5 MW wind turbines using two 1500 diesel gen sets and a 6MW load bank. We are having problem with the PF and inrush when we go to enegize these units. I have a couple of questions.
1st. When we energize our 1.5 KVA PMT's for the first time we are seeing more in rush then when we tryin this the secound time. Is this due to the transformer being cold or are the transformers windings being charged?
2nd. Is there a way to slow this inrush?
1st. When we energize our 1.5 KVA PMT's for the first time we are seeing more in rush then when we tryin this the secound time. Is this due to the transformer being cold or are the transformers windings being charged?