Hi
I am asking for some information regarding the best way pipe work for 4 water heaters that are coupled with a control panel. The setup it as follows:
[ul]
[li]The 4 water heaters are supposed to be 3 duty, and 1 alternate.[/li]
[li]The all have an equal capacity of 300L.[/li]
[li]There is a re-circulation pump attached, it feeds into the cold water supply pipe, before the first water heater.[/li]
[/ul]
I would have just used "First-In, Last Out" arrangement, but the control panel is confusing me. I was thinking of foregoing the control panel, but my supervisor said he wanted it. I do realize that there is are many options of how to set the pipe work. We aren't responsible for executing it, but I need some pointers so I can at least suggest a decent layout.
Thank you
Best Regards.
I am asking for some information regarding the best way pipe work for 4 water heaters that are coupled with a control panel. The setup it as follows:
[ul]
[li]The 4 water heaters are supposed to be 3 duty, and 1 alternate.[/li]
[li]The all have an equal capacity of 300L.[/li]
[li]There is a re-circulation pump attached, it feeds into the cold water supply pipe, before the first water heater.[/li]
[/ul]
I would have just used "First-In, Last Out" arrangement, but the control panel is confusing me. I was thinking of foregoing the control panel, but my supervisor said he wanted it. I do realize that there is are many options of how to set the pipe work. We aren't responsible for executing it, but I need some pointers so I can at least suggest a decent layout.
Thank you
Best Regards.