cadiehl
Industrial
- May 12, 2001
- 29
I'm doing a pipeline project. Only my second one. Been a piping designer in shipbuilding and various plants for over 30 years. I have a situation where I have 10" STD wall (.365") pipe going to an 8" SCH80 wall (.500") pipe. I am told I need a transition piece. I just figured this would be a reducer, but I am not sure. Usually when going from a large pipe to a smaller pipe the wall gets thinner. In this case the wall thickness is greater. What exactly is a transition piece in the pipeline world, and how to I transition in my situation? This is a 1200 psi system. The wall thicknesses I state above are required at this location in the system by the client. So I have no options. I have to make the transition.
Thanks,
CAD
Thanks,
CAD