suraiya
Materials
- Feb 9, 2002
- 24
I have a subsea gas well with reasonable amount of water content. Tieback distance to the host platform is about 5 miles, and it is an 8" pipeline. Initial calculations show that there'll be slugging. So my flow assurance engineer advises periodical pigging operation.
My question is, is there any other slug mitigation method as effective or even better than pigging? As much as possible I don't want to do subsea pigging, it is costly.