Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Piles Driven in Wrong Location

Status
Not open for further replies.

JNEnginr

Civil/Environmental
Aug 26, 2008
99
I understand that no pile driver is perfect, and that's why we typically (in our office) allow a tolerance of about 6" off of the original point where there pile was intended to be located.

My question is , how about 12" off? It's not the end of the world, some induced torsional forces, but if it was an issue, what the fix? drive another pile? I couldn't think of many other options.

Picture in plan view, multi-span grade beam oriented along x axis, with pile offset in the y direction. Steel Pipe Piles

Thanks,
 
Replies continue below

Recommended for you

if you can design a cantilevered pile cap to work then that's usually option 1.

Option 2 is drive an additional pile, whether it's just a bit further down the gb and the out of tolerance one is abandoned, or whether you use the mis-aligned pile and the new pile with a cap to provide support where it is required, that's your choice and is usually situation dependent.
 
A steel pipe pile is unlikely to have the bending capacity required for a cantilevered pile cap, so another pile may be your only option.
 
I've done a lot of this.

Before you end up wasting time on trying to make an out of tolerance pile work always have a thought about how much it's going to cost you to engineer the fix and then do really irritating detailing versus just throwing in another pile with relatively straightforward detailing and effectively no extra engineering. On shallow to moderate depth piles where the equipment is already there, the extra pile is sometimes the cheaper option.
 
Hey Everyone,

Thanks for the responses.

My go-to would b an additional pile. My issue is that they discovered this almost 2 weeks later, so no pile driver on site.

What would the torsional reinforcement look like? Say you had a 3ft wide Grade beam, then instead of the pile being centered, it was 12" to the left. How would you change the reinforcement? Additional stirrups?
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor