GalileoG
Structural
- Feb 17, 2007
- 467
Hi all,
I have concrete grade beams that span into the side of pile caps (top of pile caps is at the same elevation as top of grade beams).
I have designed the grade beam / pile cap system as a monolithic system. The contractor is proposing to pour the pile caps first, with bars sticking out of the pile caps that will lap with the grade beam top and bottom bars, the grade beams will be poured at a later time.
With this pour sequence, I have concerns about the shear interface between the pile caps and grade beams. I feel that the shear transfer between the grade beam and the pile cap would be compromised. Can this pour sequence be accommodated in any way? Is this an acceptable pour sequence? How would you address this?
Thanks!
I have concrete grade beams that span into the side of pile caps (top of pile caps is at the same elevation as top of grade beams).
I have designed the grade beam / pile cap system as a monolithic system. The contractor is proposing to pour the pile caps first, with bars sticking out of the pile caps that will lap with the grade beam top and bottom bars, the grade beams will be poured at a later time.
With this pour sequence, I have concerns about the shear interface between the pile caps and grade beams. I feel that the shear transfer between the grade beam and the pile cap would be compromised. Can this pour sequence be accommodated in any way? Is this an acceptable pour sequence? How would you address this?
Thanks!