Folks,
I have a situation with a pile cap supporting a basement slab. I have attached the proposed construction sequence.
I am concerned about punching shear especially with the two pours. I will have tie-in reinforcing between the pours and extend the reinforcing from the piles and hook into the 500mm slab.
Thoughts/Suggestions?
I have a situation with a pile cap supporting a basement slab. I have attached the proposed construction sequence.
I am concerned about punching shear especially with the two pours. I will have tie-in reinforcing between the pours and extend the reinforcing from the piles and hook into the 500mm slab.