Dec 11, 2012 #1 Tony1t Mechanical Joined Jun 18, 2012 Messages 22 Location HK Is it permit to perform an XRay examination on welds of vessel or boiler before PWHT? I do appreciated in advance.
Is it permit to perform an XRay examination on welds of vessel or boiler before PWHT? I do appreciated in advance.
Dec 12, 2012 #2 stanweld Materials Joined May 9, 2003 Messages 2,906 Location US Under ASME I & VIII, yes. Upvote 0 Downvote
Dec 16, 2012 #3 khan552 Mechanical Joined Apr 15, 2012 Messages 3 Location SA Normally in case of hydrogen service, RT (Radiography) has to be done before and after PWHT. Please let me know service of your equipment? Upvote 0 Downvote
Normally in case of hydrogen service, RT (Radiography) has to be done before and after PWHT. Please let me know service of your equipment?
Dec 17, 2012 #4 21121956 Mechanical Joined Jul 29, 2005 Messages 420 Location HN Hello everybody: TonyTao, take a look to the thread378-310323, in order to get some more information. El que no puede andar, se sienta. Upvote 0 Downvote
Hello everybody: TonyTao, take a look to the thread378-310323, in order to get some more information. El que no puede andar, se sienta.