ak1965
Mechanical
- Jul 28, 2007
- 158
We have a A335 P22 Header (16" & 21.44 mm thick) at the outlet of a double pipe heat exchnager. The Header is horizontal & has 12 nos. pipe connections at the inlet on bottom side of pipe & 01 outlet pipe connection from the middle of header on the top side of header. This equipment was designed as per ASME sect. VIII Div.1 & requires PWHT, if any welding is done on the header. Temperature in the header is approx 450 Deg C & pressure is 2 kg.cm.2/. Service is hydrocarbons.
This header receives hot process gases (hydrocarbons) with high velocity that impinge at 12 locations on Inner surface on the top portion of header. Over a period of time, 4 to 5 mm erosion has taken place at the location of impingement which is beyond corrosion allowance.
We wish to weld additional patch plates of same material (i.e. A335 P22)at all 12 locations, on the affected portion on the top side of header from outside.
1. Would it be the right approach to prevent failure of eroded part by providing a patch plate?
2. PWHT shall be required or not?
3. Can we follow ASME B31.3 instead of ASME sect VIII div. 1 that allows us to weld a patch plate with austenitic filler wire to avoid PWHT?
Please give yr expert opinion.
This header receives hot process gases (hydrocarbons) with high velocity that impinge at 12 locations on Inner surface on the top portion of header. Over a period of time, 4 to 5 mm erosion has taken place at the location of impingement which is beyond corrosion allowance.
We wish to weld additional patch plates of same material (i.e. A335 P22)at all 12 locations, on the affected portion on the top side of header from outside.
1. Would it be the right approach to prevent failure of eroded part by providing a patch plate?
2. PWHT shall be required or not?
3. Can we follow ASME B31.3 instead of ASME sect VIII div. 1 that allows us to weld a patch plate with austenitic filler wire to avoid PWHT?
Please give yr expert opinion.