UWMpe2000
Structural
- Feb 14, 2020
- 1
Here’s the scenario: There’s a three-story, precast parking garage that was built in 2017. At the second level, a large six-foot deep, precast girder (designed by the precaster) is supported on a cast-in-place concrete foundation wall (designed by the EOR). The connection was made by field welding 1/2-inch steel plates that were embedded in the precast girder and top of cast-in-place wall (i.e. not a sliding connection).
The girder and wall are starting to exhibit distress in the form of significant cracking, likely because the welded connection can’t accommodate the expansion/contraction from thermal movement and/or vibrations.
The precaster’s erection drawings show the welded connection between the embed plates. And the EOR's drawings indicate the connection should be "designed by the precast designer."
Who is ultimately responsible? The precaster, the EOR, or both?
The girder and wall are starting to exhibit distress in the form of significant cracking, likely because the welded connection can’t accommodate the expansion/contraction from thermal movement and/or vibrations.
The precaster’s erection drawings show the welded connection between the embed plates. And the EOR's drawings indicate the connection should be "designed by the precast designer."
Who is ultimately responsible? The precaster, the EOR, or both?