Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Parking Garage/Covered Parking Slopes

Status
Not open for further replies.

runoff

Civil/Environmental
Apr 19, 2006
51
To all;

I have a quick question. I have a design that the architect presented to me. He has designed a hospital that will be raised and is in the form of the letter T. The parking underneath the top portion of that T I have been able to maintain 1.5% to 2.0% slope to catch basins. However the right side of that T at the base, has been a little tricky. The bare minimum slope that is available is 0.7% from the concrete to the paving and then 1.5% to a series of catch basins. In any of your experience, do you see that this 0.7% is a problem? Again it is going to be well covered and we might get some rain that is blown in but I doubt it will be that much and then carry over from cars driving underneath. Also, the other side of that T is well sloped at 1.5% or better.

What do you great guru's think?

Runoff
 
Replies continue below

Recommended for you

Poured concrete, screed finished or better at .007, then bituminous concrete at .015? There will be no problem draining either.

Engineering is the practice of the art of science - Steve
 
If you have frost conditions and the garage is non-heated, then you should be looking for a minimum slope of 1-1/2% to minimize 'skating' areas. You may also have problems with tolerances in the pour leading to 'flat' areas.

Dik
 
I know but it will be impossible to get 1.5% inside this section of the garage. I had to come and reanalyze from the original engineers design. I am bareley getting 1.5 in some areas and bare minimum at a low portion of the parking is as low as 1.2%.

I agree with you on the skating portion. That is what I am really worried about. I liked the screed finish idea by Steve which will get the minor flows out of there. If it does flow to the other side, then there will be more of a slope in that area.

Runoff.
 
I've always gone with a bare minimum slope of 1.00-1.50% on asphalt (depending on the contractor) and a 0.5% slope on concrete.

If it's concrete and you have a nice finish on it, 0.7% shouldn't present any problems.

Some good contractor can lay asphalt at 1.00% for short stretches without creating "bird baths" or "skating areas", however, I think that is the exception more than the rule. I try to keep it at 1.50% in areas that will be seeing significant runoff.

Peace,
Stoddard
 
I try to maintain the 1-1/2% just for liability reasons. I don't have my hands on it now, but I have a couple of articles on this as well as copies of various cities building by-laws regarding slopes.

Dik
 
Thanks everyone. With the agreement of the owner, contractor, architect and myself, we went ahead with the 1.2% design. The funny thing about it is that we are only talking about 2600 to 3000 square feet of parking area that we are worried about. I had the superintendent of the job out there and myself as the paving contractor layed the paving. He did an excellent job. We ended up getting 1.3%. The architect changed up his plans and the covered parking will have coverage of 24 to 26 feet with concrete paving at 0.5 to 0.65%. Not what I really wanted but it will work. I do not think any rain will get in there anyway.

Thanks again.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor