nassau1
Civil/Environmental
- Jun 30, 2008
- 4
Question:
An architect I work with is looking to place a stairway to join two apartments. The building is a 1960 vintage one way slab construction. Slab approx 6 inches thick.
There are concrete beams at approximately 20 foot centers.
the beams run east to west and the reinforcement in the slab run north south.
The hole is contemplated to be parallel to an interior beam. The hole is to be approx 10 feet long by 4 feet wide. so approximately 16 feet of slab will be "cantilevered" until picked up.
So 10 feet of reinforcement will be cut. I am concerned about cathing the top steel that is going over the interior beam as well as supprorting the slab.
Oh yea, the owner and the architect do not want to have beams supporting the existing slab since there is a head room issue.
I am thinking of placing plates or angles all around the opening and pre-heat and welding the bars from the interior over the interior beam, and maybe also catching the bars from the north on the positive moment. I still have to carry this lot and I am thinking of loading the slab below or ??? Thoughts? Has anyone cut a hole like this before. I know, "Do not cut holes in slabs" but can it be done. Thanks
An architect I work with is looking to place a stairway to join two apartments. The building is a 1960 vintage one way slab construction. Slab approx 6 inches thick.
There are concrete beams at approximately 20 foot centers.
the beams run east to west and the reinforcement in the slab run north south.
The hole is contemplated to be parallel to an interior beam. The hole is to be approx 10 feet long by 4 feet wide. so approximately 16 feet of slab will be "cantilevered" until picked up.
So 10 feet of reinforcement will be cut. I am concerned about cathing the top steel that is going over the interior beam as well as supprorting the slab.
Oh yea, the owner and the architect do not want to have beams supporting the existing slab since there is a head room issue.
I am thinking of placing plates or angles all around the opening and pre-heat and welding the bars from the interior over the interior beam, and maybe also catching the bars from the north on the positive moment. I still have to carry this lot and I am thinking of loading the slab below or ??? Thoughts? Has anyone cut a hole like this before. I know, "Do not cut holes in slabs" but can it be done. Thanks