foxview11
Structural
- Sep 4, 2011
- 30
I just started splicing rebars of column and found out that the rebar length is 6.65m and the available full length is 12.0m. So I just cut it into two so that the rebar to be spliced will be 6.0m only which is short by 65.0cm. So I want to offset the splice from the center by 65.0cm upward to satisfy the required length of splice which is 1.3 x Ld. Does it not adversely affect the structural integrity of the the building? Please any expert on this, kindly give your opinion.
Thank you so much
Thank you so much