TQ Ahung for a detailed explanation. Btw, what is your NG price. In our case, we have 2 tiers of pricing i.e. for power plant sector and for normal industrial sector.
For power plant = USD 1.7/MMBTU (HHV)
For normal industrial = USD 3.2/MMBTU (HHV)
Another thing...do yu establish some criteria prior to decision to shutdown the GT and do the offline washing i.e. for example based on GT performance, power output, pressure drop across compressor, etc.?
Thanks
norzul