Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

NU girders, debonding outside of top flange

Status
Not open for further replies.

OSUCivlEng

Civil/Environmental
Jan 12, 2009
275
I was talking with a coworker in another office this morning. He is designing a new bridge with NU girders and was reviewing the state DOT's design requirements.

One of them was placing felt paper on the outside 9" of each side of the top flange.

This bridge is off system and tge DOT has no jurisdiction so he isn't going to follow it.

Anyone have any idea what purpose the debonding serves?
 
Replies continue below

Recommended for you

Got a drawing or picture?

Trying to get slab reaction centrally over the web of the girder?
 
I would guess that the DOT has had issues with allowing the edges of the flange to bond with the slab. Perhaps the difference in the modulus of elasticity between the slab and girders is enough to cause spalling. I suggest contacting someone at the DOT familiar with the design of that type of bridge, and ask them. There are some things we do at the DOT just because 'we've always done it that way', but the NU girders are a fairly recent invention, so the detail is likely addressing an issue that's come up.

Rod Smith, P.E.
 
Replacing the deck on PC Beams is wrought with problems. Contractors I know say it's often cheaper to replace the beams due to the labor costs of a bunch of guys with "rivet busters" doing the final concrete removal around the shear connectors while trying to avoid damaging the beams.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor